Question: Consider a project whose activities are listed in the table below. Activity E will have slack time as long as... Activity Immediate Predecessors None None

Consider a project whose activities are listed in

Consider a project whose activities are listed in the table below. Activity E will have slack time as long as... Activity Immediate Predecessors None None A,B a. Duration of E+ Duration of G Duration of D+ Duration of F c. Duration of E= Duration of D