Question: Consider a project with the following activity paths for the network: A-B-E-G(25days)A-C-D-J(28days)A-H-J(24days) If activity D is shortened by 4 days, by how many days will
Consider a project with the following activity paths for the network: A-B-E-G(25days)A-C-D-J(28days)A-H-J(24days) If activity D is shortened by 4 days, by how many days will the duration of the project be shortened