Question: Consider a project with the following information. Activity Immediate predecessors Normal time Crash time Crash cost per period A - 1 0 8 $ 2

Consider a project with the following information.
Activity Immediate predecessors Normal time Crash time Crash cost per period
A -108 $200
B A 1211 $300
C A 1110 $150
D -268 $240
E B, C, D 53 $260
What is the total cost of crashing the project by 1 time unit(s)?is the total cost of crashing the project by 1 time unit(s)?