Question: Consider a project with the following information. Activity Immediate predecessors Normal time Crash time A 10 8 B A 12 11 11 10 26 8

Consider a project with the following
Consider a project with the following information. Activity Immediate predecessors Normal time Crash time A 10 8 B A 12 11 11 10 26 8 B, C 5 3 What is the total cost of crashing the project by 1 time unit(s)? Your Answer: Crash cost per period $100 $300 $150 $220 $250 09