Question: Consider a project with the following information. Activity Immediate predecessors Normal time Crash time Crash cost per period A - 10 8 $140 B A
Consider a project with the following information.
| Activity | Immediate predecessors | Normal time | Crash time | Crash cost per period |
| A | - | 10 | 8 | $140 |
| B | A | 12 | 11 | $300 |
| C | A | 11 | 10 | $150 |
| D | - | 26 | 8 | $200 |
| E | B, C | 5 | 3 | $260 |
What is the total cost of crashing the project by 2 time unit(s)?