Question: please help me in this Question 7 (1 point) Consider a project with the following information. Activity Immediate predecessors Normal time Crash time 10 8
please help me in this
Question 7 (1 point) Consider a project with the following information. Activity Immediate predecessors Normal time Crash time 10 8 B A 12 11 11 10 D A 11 8 E B, C, D 5 3 What is the total cost of crashing the project by 2 time unit(s)? Crash cost per period $200 $300 $150 $220 $250 Your