Question: Consider an assembly line with 3 sequential operations A , B , and C with processing rates 1 0 , 4 0 , and 3
Consider an assembly line with sequential operations A B and C with processing rates and parts per hour, respectively.
Suppose there is one dedicated worker for A and B Abe and one dedicated worker for C Chris However, both workers are perfectly crosstrained.
HINT: The first step is to calculate the cycle times of operations A B and C
a What is the process capacity in parts per hour?