Question: Consider an assembly line with 3 sequential operations A, B, and C with processing rates 10, 40, and 30parts per hour, respectively. Suppose there is
Consider an assembly line with 3 sequential operations A, B, and C with processing rates 10, 40, and 30parts per hour, respectively. Suppose there is one dedicated worker for A and B (Abe) and one dedicated worker for C (Chris). However, both workers are perfectly cross-trained.
(a)What is the process capacity in parts per hour?
(b)Suggest a way of reassigning tasks to Abe and Chris so as to maximize the process capacity. What is the maximum process capacity?
What is the cycle time of the process on a day when Chris is absent, and Abe is the only worker
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts