Question: Consider an assembly line with 3 sequential operations A, B, and C with processing times per part of 10, 20, and 40 minutes, respectively. Operations
Consider an assembly line with 3 sequential operations A, B, and C with processing times per part of 10, 20, and 40 minutes, respectively. Operations A and B are performed by Peter, and operation C by Mary. The bottleneck worker is:
A) Peter
B) Mary
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts