Question: Consider the 3 estimates in the table below and assume that the 5 activities are probabilistic. Utilize PERT to solve the following questions 1. How
Consider the 3 estimates in the table below and assume that the 5 activities are probabilistic. Utilize PERT to solve the following questions

1. How many days will it take to complete the project with a 50% probability?
2. How many days will it take to complete the project with a 90% probability?
Assuming all the activities are done in the normal time, suppose that the following five activities are probabilistic. Show the schedule for the following two cases. A) Find the completion time of the project for fifty percent chance of completion. B) Find the completion time of the project for 90 percent chance of completion. Step Most Likely Optimistic Pessimistic 20 A. Prepare Preliminary Specifications B. Excavate Foundation C. Pour Foundation D. Electric Work N. Paint Exterior auuwStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock