Question: Consider the activities whose sequence is described by the following table. Which activities are on the critical path? Activity Immediate Predecessor(s) Time (Days) 5 A

Consider the activities whose sequence is

Consider the activities whose sequence is described by the following table. Which activities are on the critical path? Activity Immediate Predecessor(s) Time (Days) 5 A 2 A B AN C 4 D B 5 E B 5 F C 5 G 2 10I E, F D H 3 1 G H 5