Question: Consider the following activity schedule for a project: Activity ES EF LS LF Slack CP A 0 3 0 3 B 3 6 5 8

Consider the following activity schedule for a project:
Activity
ES
EF
LS
LF
Slack
CP
A
0
3
0
3
B
3
6
5
8
C
3
8
3
8
D
8
12
8
12
E
8
11
9
12
F
12
14
12
14
What is the completion time associated with Activity B?