Question: Consider the following CPM project. Activity Normal Time Crash Time Normal Cost Crash Cost A 12 8 2120 3070 B 14 12 1810 2090 C
Consider the following CPM project.
| Activity | Normal Time | Crash Time | Normal Cost | Crash Cost |
| A | 12 | 8 | 2120 | 3070 |
| B | 14 | 12 | 1810 | 2090 |
| C | 12 | 11 | 9550 | 10610 |
| D | 11 | 8 | 5010 | 6150 |
| E | 8 | 3 | 3130 | 4250 |
| F | 9 | 5 | 3630 | 4150 |
| G | 16 | 11 | 15870 | 16970 |
| H | 13 | 9 | 8170 | 9340 |
a)
Calculate the carshing cost per period for each of the activities of the project.
| Activity | Crash Cost per period |
| A | Round your answer to 1 decimal place. |
| B | Round your answer to 1 decimal place. |
| C | Round your answer to 1 decimal place. |
| D | Round your answer to 1 decimal place. |
| E | Round your answer to 1 decimal place. |
| F | Round your answer to 1 decimal place. |
| G | Round your answer to 1 decimal place. |
| H | Round your answer to 1 decimal place. |
b)
Suppose that the critical path of the project is A-C-E-F-H. Which activity would you select to crash and at what cost per period?
| Activity to crash = | |
| Crashing cost per priod = | Round your answer to 1 decimal place. |