Question: Consider the following data for a project to install a new server at the Northland Pines High School:ActivityActivity Time ( days ) Immediate Predecessors )

Consider the following data for a project to install a new server at the Northland Pines High School:ActivityActivity Time (days)Immediate Predecessors)2B4A5D21F8B, CG3D, EH5F-4FJ7G, H, Ia. Draw the network diagram.b. Calculate the critical path for this project.G. How much slack is in each of the activities G, H, and I?