Question: a. for the project to install a new server af the Nortanx Pines HS, what is the latest start time for activity C? b. how
a. for the project to install a new server af the Nortanx Pines HS, what is the latest start time for activity C?
b. how mang paths exist for the project to install a new server at the HS? & what is the critical path/ its lenght?
c. what is the slack time for activity D & G?
d. for some technical reasons, activity time for F has increased from 8 to 9 days, the minimum project duration will now increase by how many days?