Question: Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) A
Consider the following data for a project to install a new server at the Northland Pines High School:
Activity Activity Time (days) Immediate Predecessor(s) A 3 - B 3 A C 5 A D 3 B E 1 B F 6 B, C G 3 D, E H 4 F I 3 F J 7 G, H, I
b. Calculate the critical path for this project.
The critical path is A-C-F-H-J and the project duration is 25 days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G, H, and I?
| Activity | Activity Time (days) | On critical path? | Slack (days) |
| G | 3 |
|
|
| H | 4 |
|
|
| I | 3 |
|
|