Question: Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) A
Consider the following data for a project to install a new server at the Northland Pines High School:
| Activity | Activity Time (days) | Immediate Predecessor(s) |
| A | 3 | |
| B | 3 | A |
| C | 6 | A |
| D | 3 | B |
| E | 1 | B |
| F | 7 | B, C |
| G | 3 | D, E |
| H | 3 | F |
| I | 5 | F |
| J | 5 | G, H, I |
How much slack is in each of the activities G, H, and I?
| Activity | Activity Time (days) | On critical path? | Slack (days) |
| G | 3 | No Yes | enter your response here |
| H | 3 | Yes No | enter your response here |
| I | 5 | Yes No | enter your response here |