Question: Consider the following data for MRP. Develop the material requirements plan for item B and C and answer the questions below. MPS start: End item

Consider the following data for MRP. Develop the material requirements plan for item B and C and answer the questions below.

MPS start:

End item

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

A

120

80

Bill of materials:

  • End item A is made of 1 unit of item B.
  • Item B is made of 2 units of item C.

MRP-related information for each item:

Item

Leadtime (weeks)

Lot sizing

Safety stock

On-hand inventory

Scheduled receipts

B

1

L4L

0

30

60 in week 1

C

2

FOQ (50)

20

80

None

What is the gross requirement for item B in Week 3? units

What is the projected available balance of item B at the end of week 1? units

What is the gross requirement for item C in Week 4? units

What should be the planned order release for item C in week 2? units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!