Question: Consider the following data for MRP. Develop the material requirements plan for items B and C and answer the questions below. MPS start: End Week
Consider the following data for MRP. Develop the material requirements plan for items B and C and answer the questions below. MPS start: End Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 item A 50 80 Bill of materials: End item A is made of 1 unit of item B. Item B is made of 2 units of item C. MRP-related information for each item: Item B Leadtime Lot Safety stock (weeks) sizing Requirement L4L Available On-hand inventory 30 Scheduled receipts None