Question: Consider the following data for MRP. Develop the material requirements plan for item B and C, and answer questions 32-36. MPS start: End item Week
Consider the following data for MRP. Develop the material requirements plan for item B and C, and answer questions 32-36.
MPS start:
| End item | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 |
| A |
|
| 120 | 80 |
|
Bill of materials:
- End item A is made of 1 unit of item B.
- Item B is made of 2 units of item C.
MRP-related information for each item:
| Item | Leadtime (weeks) | Lot sizing | Safety stock | On-hand inventory | Scheduled receipts |
| B | 1 | L4L | 0 | 30 | 60 in week 1 |
| C | 2 | FOQ (50) | 20 | 80 | None |
1. What is the gross requirement for item B in Week 3?
2. What is the projected available balance of item B at the end of week 1?
3. What should be the planned order release for item B in week 2?
4.What is the gross requirement for item C in Week 4?
5.What should be the planned order release for item C in week 2?
Step by Step Solution
There are 3 Steps involved in it