Question: Consider the following data for MRP. Develop the material requirements plan for items C, D, and E. MPS start: End Item Week 1 Week 2

Consider the following data for MRP. Develop the material requirements plan for items C, D, and E.

MPS start:

End Item

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

A

120

110

Bill of materials:

End item A is made of 2 units of component C and 1 unit of subassembly D.

Subassembly D is made of 1 unit of component E.

Item

Leadtime

(Weeks)

Lot sizing

Safety stock

On-hand inventory

Scheduled receipts

C

2

POQ (2)

30

120

120 in week 2

D

1

L4L

0

30

60 in week 1

E

1

FOQ (50)

20

50

None

1. The gross requirement for Subassembly D in Week 3 is 120 units.

a. True

b. False

2. Which of the following statements about the MRP plan for item C is true?

a.Its gross requirement in week 3 is 120 units

b.It has a planned order release of 30 units in week 1

c.Its projected available balance at the end of week 2 is 90 units

d.It has a planned receipt of 250 units in week 3

e.None of the above.

3. What should be the planned receipt for item D in week 3?

a.0 unit

b.30 units

c.110 units

d.170 units

e.250 units

4. What should be the planned receipt for item E in week 3?

a. 0 unit

b. 40 units

c. 110 units

d. 150 units

e. 220 units

Step by Step Solution

3.63 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 The total requirement for subassembly D in week 3 is 120 units ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!