Question: Consider the following information about a small project: Task Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day A 5 None 4 $6,500
Consider the following information about a small project:
| Task | Duration (days) | Immediate Predecessors | Shortest Time Possible | Acceleration Cost per day |
| A | 5 | None | 4 | $6,500 |
| B | 10 | A | 9 | $5,000 |
| C | 8 | A | 7 | $7,000 |
| D | 6 | B | 3 | $6,000 |
| E | 7 | C | 6 | $6,000 |
| F | 3 | C | 2 | $7,000 |
| G | 4 | D,E,F |
A) Find the cost-effective way to reduce the completion time by 3 days. For example, if your answer is to accelerate task A by 1 day, put down A by 1 in the blank. When you need to accelerate multiple tasks at the same time, please identify them in a single step. For example, if your answer is to accelerate B and C both by 1 day, put down BC by 1 in the blank. Step 1: Accelerate task(s) ____ day(s) Step 2: Accelerate task(s) ____ day(s) Step 3: Accelerate task(s) ____ day(s)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts