Question: Consider the following information: Demand rate ( D ) = 2 9 0 units per hour Lead time ( T ) = 6 hours Container
Consider the following information:
Demand rate units per hour
Lead time hours
Container capacity units
Safety factor
a The number of kanban production cards is Enter your response rounded up to the next whole number.
b The cards will represent hours' worth of demand. Enter your response rounded to one decimal place.
c Suppose the lead time is reduced to five hours. The number of kanban production cards is
Enter your
response rounded up to the next whole number.
The cards will represent hours' worth of demand. Enter your response rounded to one decimal place.