Question: Consider the following partially completed PERT table (Question 11 data) Activity Predecessor Optimistic time Most likely time Pessimistic time Expected time Variance EF LF Slack

  1. Consider the following partially completed PERT table (Question 11 data)

    Activity

    Predecessor

    Optimistic time

    Most likely time

    Pessimistic time

    Expected time

    Variance

    EF

    LF

    Slack

    CP

    A

    -

    1

    1.5

    5

    2

    0.444

    2

    2

    B

    A

    2

    4

    5

    3.833

    0.250

    5.833

    5.833

    C

    A

    1

    2

    3

    2

    0.111

    4

    6.83

    D

    B,C

    3.5

    5

    6.5

    5

    0.250

    10.83

    11.83

    E

    B

    4

    5

    12

    6

    1.778

    11.83

    11.83

    F

    C,D,E

    5

    9

    ??

    9

    1.778

    20.83

    20.83

    G

    E

    6.5

    7.5

    11.5

    8

    ??

    19.83

    20.83

    The variance of Job G is

    0.6944

    0.25

    0.1111

    1.777

    0.4444

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!