Question: Consider the following partially completed PERT table (Question 11 data) Activity Predecessor Optimistic time Most likely time Pessimistic time Expected time Variance EF LF Slack
-
Consider the following partially completed PERT table (Question 11 data)
Activity
Predecessor
Optimistic time
Most likely time
Pessimistic time
Expected time
Variance
EF
LF
Slack
CP
A
-
1
1.5
5
2
0.444
2
2
B
A
2
4
5
3.833
0.250
5.833
5.833
C
A
1
2
3
2
0.111
4
6.83
D
B,C
3.5
5
6.5
5
0.250
10.83
11.83
E
B
4
5
12
6
1.778
11.83
11.83
F
C,D,E
5
9
??
9
1.778
20.83
20.83
G
E
6.5
7.5
11.5
8
??
19.83
20.83
The variance of Job G is
0.6944
0.25
0.1111
1.777
0.4444