Question: Consider the following project: A B C D E F 13 36 46 31 28 27 What is the project completion time? A w E

Consider the following project:

Consider the following project: A B C D E F 13 36

A B C D E F
13 36 46 31

28

27

What is the project completion time?

A w E Start End B D F