Question: Consider the following project. a ) Develop the project cash flow and S - curve diagrams for the early and late start durations before any
Consider the following project.
a Develop the project cash flow and Scurve diagrams for the early and late start durations
before any of the activities are crashed. For this part of the problem. You can use Excel to
develop these curves, if you like. points
b Crash the project to the least possible duration. Make sure to record the total direct cost
and duration for each iteration. points
c Assume the project overhead is of the total direct cost. The owner wants the project
to be completed in weeks or less and will charge a penalty of $ for each week
of delay beyond weeks. Determine the optimum project duration and total price.
points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
