Question: Consider the following Project activities. table [ [ Activity , table [ [ Immed . ] , [ Predec . ] ] ,

Consider the following Project activities.
\table[[Activity,\table[[Immed.],[Predec.]],\table[[Optimistic],[Time (Hr)]],\table[[Most Likely],[Time (Hr)]],\table[[Pessimistic],[Time (Hr)]]],[A,-,4,6,8],[B,-,1,4.5,5],[C,A,3,3,3],[D,A,4,5,6],[E,A,0.5,1,1.5],[F,B,C,3,4,5],[G,B,C,1,1.5,5],[H,E,F,5,6,7],[I,E,F,2,5,8],[J,D,H,2.5,2.75,4.5],[K,G,I,3,5,7]]
Calculate the probability that the critical path of the project is completed within 24 hours.
Formulas and the Standard Normal Distribution table can be found in Lecture notes published on D2L.
Note: A network diagram is helpful to find the critical path, but you do not need to calculate ES,EF,LS,LF for this assignment. Use excel for your calculations.
 Consider the following Project activities. \table[[Activity,\table[[Immed.],[Predec.]],\table[[Optimistic],[Time (Hr)]],\table[[Most Likely],[Time (Hr)]],\table[[Pessimistic],[Time (Hr)]]],[A,-,4,6,8],[B,-,1,4.5,5],[C,A,3,3,3],[D,A,4,5,6],[E,A,0.5,1,1.5],[F,B,C,3,4,5],[G,B,C,1,1.5,5],[H,E,F,5,6,7],[I,E,F,2,5,8],[J,D,H,2.5,2.75,4.5],[K,G,I,3,5,7]] Calculate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!