Question: Consider the following project: Activity A Immediate Predecessors A A B E C F B,C G D, E H C What is the latest start
Consider the following project: Activity A Immediate Predecessors A A B E C F B,C G D, E H C What is the latest start time for activity G? Multiple Choice 15 14 13 12 BU C D Durations (weeks) 5 3 2 3 7 3 62