Question: I need help on this question Consider the following project: Activity mmeadiate Durations Predecessors (weeks) A 6 B A 3 A 2 B 3 E

I need help on this question

Consider the following project: Activity mmeadiate Durations Predecessors (weeks) A 6 B A 3 A 2 B 3 E C 8 F B , C 3 G D , E H C 2 What is the latest start time for activity G? Multiple Choice 17 O 15 14 O 16