Question: Consider the following project. Activity Dependency Normal Duration (days) A - 6 B A 7 C A 6 D A 7 E C,D 6 F

Consider the following project.

Activity Dependency Normal Duration (days)
A - 6
B A 7
C A 6
D A 7
E C,D 6
F B 8
G E,F 1

a) Draw the network diagram. (2 marks)

b) Determine the critical path for the project. (2 marks)

c) How much time is needed to complete this project? (1 mark)

d) Determine the slack for each activity. (1 mark)

e) Construct a Gantt chart for this project. (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!