Question: Consider the following project. Activity Immediate Predecessor Activity Time ( days ) A - - 3 B - - 4 C A 4 D A

Consider the following project.
Activity
Immediate Predecessor
Activity Time (days)
A
--
3
B
--
4
C
A
4
D
A
6
E
B
5
F
C,D
4
G
E,F
7
What is the critical path?