Question: Consider the following project. Activity Immediate Processor Activity Time (days) A 6 00 8 , 5 D B 4 E 7 F C D G

Consider the following project. Activity
Consider the following project. Activity
Consider the following project. Activity Immediate Processor Activity Time (days) A 6 00 8 , 5 D B 4 E 7 F C D G D 6 6 6 H E, F, G Determine the critical path. O ACEI BDFH ACEH ! Consider the following project. Activity Immediate Processor Activity Time (days) A 6 B 8 A, B 5 moo B 4 7 F CD G D 3 6 5 H E, F, G Determine the Early Start time for Activity H. O 20 days 25 days 16 days 18 days