Question: Consider the following project network and cost / time information. This project has a $ 1 0 0 ? day indirect cost: What is the
Consider the following project network and costtime information. This project has a $ day
indirect cost:
What is the direct cost of completing this project using the normal times? Enter a numerical
value without $ or or
What is the total cost of completing this project using the normal times? Enter a numerical
value without $ or or
If you were asked to reduce the project completion time by one time unit, which activity would
you crash?
What is the indirect cost of this project if we reduce its completion time by two days? Enter a
numerical value without $ or or
What is the total cost of this project if we reduce its completion time by two days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
