Question: Consider the following project network and cost / time information. This project has a $ 6 0 / day indirect cost: Activity Precedence Normal Time

Consider the following project network and cost/time information. This project has a $60/day indirect cost:
Activity Precedence Normal Time Crash Time Normal Cost Crash Cost
A -545075
B A 327080
C A 425060
D B 4190150
E C 1 Can't be crashed 50-
F D, E 31200600
What is the direct cost of completing this project using the normal times? (Enter a numerical value without $ or ,)'