Question: Consider the following project network: F A C E finish start B D Activity Mean Time Variance (weeks) 3 A 9 8 B 4 7

Consider the following project network: F A C E

Consider the following project network: F A C E finish start B D Activity Mean Time Variance (weeks) 3 A 9 8 B 4 7 2 D 7 3 2 1 E F 4 2 What is the standard deviation of the length of the critical path? 06 O 5 0 2.45 03.12