Question: Consider the following project network: F A E finish start B D Activity Mean Time Variance (weeks) 3 9 8 7 4 2 A B

Consider the following project network: F A E

Consider the following project network: F A E finish start B D Activity Mean Time Variance (weeks) 3 9 8 7 4 2 A B D E F 7 3 2 1 2 4 What is the earliest finish time of activity D