Question: Consider the following project network: F C E E finish start B D Activity Variance (weeks) Mean Time 9 8 3 A B 4 7

Consider the following project network: F C E E

Consider the following project network: F C E E finish start B D Activity Variance (weeks) Mean Time 9 8 3 A B 4 7 2 D E F 7 2 4 3 1 2 What is the earliest finish time of the project? O 13 018 O 16 015