Question: Consider the following project network: F E finish start B D Activity Mean Time Variance (weeks) 3 4 A 9 B 8 2 D E

Consider the following project network: F E

Consider the following project network: F E finish start B D Activity Mean Time Variance (weeks) 3 4 A 9 B 8 2 D E F 7 7 2 4 3 1 2 What is the critical path? B-D-F O A-F-E O A-C-E O B-D-E