Question: Consider the following project: table [ [ Activity , Time,Predecessor ] , [ A , 1 2 , - ] , [ B ,

Consider the following project:
\table[[Activity,Time,Predecessor],[A,12,-],[B,10,-],[C,9,A],[D,15,A],[E,7,B],[F,8,D, E],[G,13,C, F]]
Which activity has a slack time that is different from all others?
Project Management.xlsx q,
q,
None of the above answers is correct.
B
C
E
 Consider the following project: \table[[Activity,Time,Predecessor],[A,12,-],[B,10,-],[C,9,A],[D,15,A],[E,7,B],[F,8,D, E],[G,13,C, F]] Which activity has a