Question: 5. Consider the following project. Task Description Duration (Weeks) Immediate Predecessors A Require Analysis 6 - B System Design 15 A C Programming 25 B
5. Consider the following project.
Task Description Duration (Weeks) Immediate Predecessors A Require Analysis 6 - B System Design 15 A C Programming 25 B D Telecoms 16 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/ Support 5 G I Handover and Go-Live 5 H a. Draw a project network b. What are the critical activities? c. Develop the activity schedule for the project d. What activity has the most slack time?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts