Question: Operations Management 5. Consider the following project. Task Description Duration (Weeks) Immediate Predecessors A Require Analysis 6 - B System Design 15 A C Programming
Operations Management
5. Consider the following project.
| Task | Description | Duration (Weeks) | Immediate Predecessors |
| A | Require Analysis | 6 | - |
| B | System Design | 15 | A |
| C | Programming | 25 | B |
| D | Telecoms | 16 | B |
| E | Hardware Installation | 30 | B |
| F | Integration | 10 | C, D |
| G | System Testing | 10 | E, F |
| H | Training/ Support | 5 | G |
| I | Handover and Go-Live | 5 | H |
- Draw a project network
- What are the critical activities?
- Develop the activity schedule for the project
- What activity has the most slack time?