Question: Consider the following project, with three time estimates for each activity where activity times are in days. Find the following: (i) The network (ii) All

Consider the following project, with three time estimates for each activity where activity times are in days. Find the following: (i) The network (ii) All expected activity times, variances and slacks. (iii) The critical path and expected completion time. (iv) The probability of the project will be done in 23 days.

(v) The completion time corresponding to 95% probability. Consider the following project, with three time

Activity to to I to tinto to Predecessors a 1 4 7 b 2 2 2 2 5 8 a d 3 4 5 a - 4 6 8 e e f C, 6 c, b 0 3 016 6 9 g d, c

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!