Question: Consider the following sequential production process with four machines A , B , C , and D ( 4 workers operate these machines respectively, one

Consider the following sequential production process with four machines A, B, C, and D (4 workers operate these machines respectively, one worker per machine).Machine AMachine DFramerFinisher5 minutes minutesMachine BMachine CHandlerStringer3 minutes10 minutes2All flow units need to move through all the above stages sequentially, with the designated task time indicated above. Assume the labor rate is $15 per hour per employee, and the process is operated on a continual basis, what is the average labor cost per unit of product produced? $50 $20