Question: Consider the following work breakdown structure: Start Finish Duration Estimate (Days) Activity Node Node Optimistic. Most Likely Pessimistic 1 2 9 15 21 B 1

Consider the following work breakdown structure:
Consider the following work breakdown structure: Start Finish Duration Estimate (Days) Activity Node Node Optimistic. Most Likely Pessimistic 1 2 9 15 21 B 1 3 13 21 23 2 4 6 9 18 5 23 35 47 E 5 19 26 27 F 4 6 23 29 41 5 6 14 20 26 H 6 7 2 5 8 within what amount of time (in weeks) is there a 90 percent probability that the critical path for this project will be completed? (Please keep 2 digits after the decimal point.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!