Question: Consider the following work breakdown structure: ActivityStart NodeFinish NodeTime Estimates ( wks ) totmtpA 1 2 1 1 2 0 2 9 B 2 3

Consider the following work breakdown structure:
ActivityStart NodeFinish NodeTime Estimates (wks)totmtpA12112029B23258C24183042D3471013E14314043
What is the probability that the critical path for this project will be completed within 52 weeks?
Multiple Choice
.1554
.3108
.3466
.6554
.8277