Question: Consider the following work breakdown structure: Duration (Days) Activity Preceding Task Optimistic Most Likely Pessimistic A - 41 50 59 B - 54 60 66
Consider the following work breakdown structure:
| Duration (Days) | ||||
| Activity | Preceding Task | Optimistic | Most Likely | Pessimistic |
| A | - | 41 | 50 | 59 |
| B | - | 54 | 60 | 66 |
| C | A | 58 | 70 | 82 |
| D | B | 32 | 41 | 44 |
What is the estimated expected (mean) time for activity D?