Question: Consider the following work breakdown structure: Duration (Days) Activity Preceding Task Optimistic Most Likely Pessimistic A - 41 50 59 B - 54 60 66

Consider the following work breakdown structure:

Duration (Days)
Activity Preceding Task Optimistic Most Likely Pessimistic
A - 41 50 59
B - 54 60 66
C A 58 70 82
D B 32 41 44

What is the estimated expected (mean) time for activity D?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!