Question: Consider the following work breakdown structure: Duration (days) Activity Preceding Task 100 Optimistic 41 54 58 32 Most Likely 50 60 70 41 Pessimistic 59

Consider the following work breakdown structure:
Consider the following work breakdown structure: Duration (days) Activity Preceding Task 100 Optimistic 41 54 58 32 Most Likely 50 60 70 41 Pessimistic 59 66 82 44 A B What is the estimated standard deviation in the time for activity D? Multiple Choice o days 2 days 3 days A 4 days 12 days