Question: Consider the following work breakdown structure: Duration (days) Preceding Task Activity A B. Pessimistic Optimistic 41 54 58 Most Likely 50 59 66 A D

Consider the following work breakdown structure:

Consider the following work breakdown structure: Duration (days) Preceding Task Activity A B. Pessimistic Optimistic 41 54 58 Most Likely 50 59 66 A D 60 70 B. 32 82 44 41 What is the estimated slack time for activity D? Multiple Choice O days 19 days 20 days 79 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!