Question: Consider the following work breakdown structure: Duration (days) Preceding Task Activity A B on P Optimistic 41 54 58 32 Most Likely 50 6e 70

Consider the following work breakdown structure:
Consider the following work breakdown structure: Duration (days) Preceding Task Activity A B on P Optimistic 41 54 58 32 Most Likely 50 6e 70 41 Pessimistic 59 66 82 44 B What is the probability that this project will be completed within 130 days? Multiple Choice 8413 90 9544 9772 9987

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!