Question: Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U,V - - - U W 35 50 65
Consider the following work breakdown structure:
| Duration Estimates (Days) | ||||||||||
| Activity | Precedes | Optimistic | Most Likely | Pessimistic | ||||||
| Start | U,V | - | - | - | ||||||
| U | W | 35 | 50 | 65 | ||||||
| V | W,X | 28 | 40 | 52 | ||||||
| W | Z | 26 | 35 | 44 | ||||||
| X | Y | 28 | 40 | 52 | ||||||
| Y | Z | 26 | 29 | 38 | ||||||
| Z | End | 36 | 60 | 84 | ||||||
What is the estimated slack time for activity W?
Multiple Choice
-
35 days
-
25 days
-
0 day
-
45 days
-
85 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
